Code: MA-00004
Location: Thai Binh
Land area: 27.2 ha (Phase 1: 14 ha, Phase 2: 13.2 ha)
Purpose: Transfer 100%
Legal status and project progress:
The project had an investment policy decision in 2019 and a feasibility study approval in August 2021. EVN has agreed in principle to purchase electricity from the project (November 2020). Currently, the PPA contract has not been signed because it has to wait for the Government's new price policy related to wind power projects.
Contact information: support@ipavietnam.org l +84-83-555-3388