Code: FDI-00021
Project status: Completed licensing procedure
Objective: Manufacturing Garments
Land area: N/A
Investment capital: $7 - $10 million
Location: Hung Yen
Project description:
Producing and processing clothes, underwear, garment accessories. The progress of the project implementation is as follows:
Phase I:
Carrying out legal procedures: From December 2021 to February 2022.
Installation of machinery and equipment: From March 2022 to April 2022.
Putting the entire first phase of the project into official operation: From May 2022.
Phase II:
Installation of machinery and equipment: From November 2023 to December 2023.
Putting the entire phase II of the project into official operation: From January 2024.